HCP Deep Schedule Analysis Report


This analysis and report prepared for

Sample Project
John Smith

by Tal Levanon, MSc, PMI-SP
HCP Project Management Consulting
info@hcp-consulting.com
www.hcp-consulting.com

October 24, 2009

 


Table of Contents


1. Executive Summary

1.1. Key Schedule and Analysis Statistics
1.2. Project Success Expectation
1.3. Schedule Integrity Analysis Highlights
1.4. HCP Critical Path Analysis Highlights

2. Schedule Integrity Analysis Report

2.1. Schedule Integrity Overview
2.2. Activities Unlinked to Successors
2.3. Start-to-Finish (SF) Links
2.4. Activities with Predated Successors
2.5. Activities with Calendar Inconsistencies
2.6. Overdue Activities

3. HCP Critical Path Analysis Report

3.1. HCP Critical Path Analysis Overview
3.2. Activities in the HCP Critical Paths
3.3. Opportunities for Bringing Forward the Schedule's End Date
3.4. Overlapping Activities in the HCP Critical Paths
3.5. Activities in the HCP Near-critical Paths
3.6. Difficult-to-Track Activities
3.7. Unstarted (Overdue) Paths
3.8. Identified HCP Paths
3.9. Redundant HCP Paths
3.10. Enhanced Schedule File

Disclaimer

 


1. Executive Summary

1.1. Key Schedule and Analysis Statistics

Key Schedule and Analysis Dates

Earliest start date in schedule: August 18, 2009
Scheduled project end date: May 25, 2010
Date range analyzed: August 18, 2009 – May 25, 2010
Effective date of analysis: September 12, 2009

Activity and Link Counts

Number of activities in schedule: 166
Number of links in schedule: 188

 


1.2. Project Success Expectation

The HCP analysis of this schedule yielded insights into the expected success levels of various aspects of the project. Note that all of these estimations are based solely on our conclusions regarding the robustness and integrity of the schedule, without actually analyzing any actual cost or spec data.


    1 2 3 4 5 6 7
     Very 
Low
 Low              Med              High   Very 
High
Overall Overall expectation of project     
success
           
On Time Expectation that the project
will be completed on time
           
On Spec Expectation that the project
will be completed per spec
           
On Budget    Expectation that the project
will be completed on budget
           

 


1.3. Schedule Integrity Analysis Highlights

  1. We identified 6 activities not connected to any successor, representing 3.6% of all project activities (6 of these activities are not yet completed, representing 3.6% of all project activities). Activities without successors are interpreted by the HCP analysis as end points in the schedule. To ensure an effective HCP analysis, we recommend that all such activities be reviewed and corrected, if necessary, before resubmitting the schedule for a full HCP analysis. Refer to section 2.2 for details.
  2. We identified 2 start-to-finish (SF) links in the schedule (this represents 1.1% of all links in the schedule). SF links specify that a successor activity ends when the predecessor activity begins. In general, it is not recommended to utilize this type of link because it can cause difficulties in executing the project. To ensure an effective HCP analysis, we recommend that all such links be reviewed and corrected, if necessary, before resubmitting the schedule for a full HCP analysis. Refer to section 2.3 for details.
  3. We identified 3 instances in which a successor activity is scheduled to begin before the activities which precede them (this represents 1.8% of all activities in the schedule). This obviously impossible situation, without management attention, has the potential to cause serious project delays. To ensure an effective HCP analysis, we recommend that all such activities be reviewed and corrected, if necessary, before resubmitting the schedule for a full HCP analysis. Refer to section 2.4 for details.
  4. We found that the specified durations of all activities are consistent with their defined start date, end date and the schedule's calendar. This is a good indicator of high schedule integrity.
  5. We identified 3 overdue activities (representing 1.8% of all activities in the schedule), which should have already been started as of the effective date of this analysis (September 12, 2009). Refer to section 2.6 for details.

 


1.4. HCP Critical Path Analysis Highlights

  1. The 2 paths found in the schedule with the longest duration (180.1 days), referred to herein as the "HCP critical paths," are not both identical to the conventional (CPM) critical path(s). This means that there are 2 previously-hidden critical paths in the schedule (consisting of a total of 52 activities) requiring urgent management attention. Without this attention, the on-schedule completion of the project is in jeopardy. Refer to section 3.2 for details.
  2. The schedule's end date could possibly be brought forward by up to 20.8 days, by addressing lags and/or constraints among activities within the HCP critical path. Refer to section 3.3 for details.
  3. We identified no instances of overlapping activities in the HCP critical paths. This indicates a plan with relatively low risk of falling behind schedule at any particular point in the project. However, we recommend seeking out opportunities where activities found in the HCP critical paths may be performed in parallel. While doing so will add a degree of risk at these particular points in time, it will add a buffer at the end of the project, thus increasing the probability of completing the entire project on schedule. Refer to section 3.2 for the activities contained within the HCP critical paths.
  4. Of the schedule's 166 activities, we identified 52 activities within the 2 HCP critical paths and within another 61 "HCP near-critical paths" – this indicates a minimally risky project. These activities require management attention. Refer to section 3.5 for details.
  5. We identified 19 activities as difficult-to-track. Refer to section 3.6 for details.
  6. We identified 9 unstarted (overdue) paths in the schedule. This could indicate a number of different potential problems which require urgent management attention. Refer to section 3.7 for details.

 


2. Schedule Integrity Analysis Report

2.1. Schedule Integrity Overview

Key Schedule and Analysis Dates

Earliest start date in schedule: August 18, 2009
Scheduled project end date: May 25, 2010
Date range analyzed: August 18, 2009 – May 25, 2010
Effective date of analysis: September 12, 2009

Activity and Link Counts

Number of activities in schedule: 166
Number of links in schedule: 188

Summary Count of Schedule Integrity Issues

Activities unlinked to successors 6
Start-to-finish links 2
Activities with predated successors 3
Activities with calendar inconsistencies 0
Overdue activities 3

 


2.2. Activities Unlinked to Successors

We identified 6 activities not connected to any successor, representing 3.6% of all project activities (6 of these activities are not yet completed, representing 3.6% of all project activities). Activities without successors are interpreted by the HCP analysis as end points in the schedule.

Analysis Warning: To maximize the effectiveness of the HCP analysis, we recommend that these activities be reviewed and corrected, if necessary, before resubmitting the schedule for a full HCP analysis.

# Activity ID WBS % Completed
1912019_M.5 0.0%
Reverse the swing direction of the door located at the cleaner's room in 7in Implant to allow a vacuum pump installati
21132019_P.6 0.0%
RTP
31212019_Q.7 0.0%
RTP
41822019_R.8.15.5 0.0%
Dock Date for pumps
51952019_U 0.0%
Convert Channel B - 2 from WM Nit to LT Ox in Diffusion
61972019_W 0.0%
Finish MS

 


2.3. Start-to-Finish (SF) Links

We identified 2 start-to-finish (SF) links in the schedule (representing 1.1% of all links in the schedule). SF links specify that a successor activity ends when the predecessor activity begins. In general, it is not recommended to utilize this type of link because it can cause difficulties in executing the project.

Analysis Warning: Unless the schedule was logically designed starting at the end of the project and working backwards, we recommend that all SF links are replaced with finish-to-start, finish-to-finish or start-to-start links. If these links must remain in the schedule, please let us know so that we can fine-tune our HCP analysis to take this into account.

Note: Each pair of activities is listed with the predecessor first, followed by its successor.

# Activity ID WBS % Completed Start Date End Date
11842019_R.8.15.7 0.0%04/29/2010 04:12pm 05/13/2010 04:12pm
Install New T&L Coat Track System #9 & #10 at the location shown on the drawing
1822019_R.8.15.5 0.0%12/16/2009 04:12pm 12/21/2009 04:12pm
Dock Date for pumps
21962019_V 0.0%12/28/2009 08:00am 01/15/2010 05:00pm
Convert NGR Channel to Norob Dr. in Diffusion (optional)
1952019_U 0.0%12/07/2009 08:00am 12/25/2009 05:00pm
Convert Channel B - 2 from WM Nit to LT Ox in Diffusion

 


2.4. Activities with Predated Successors

We identified the following 3 instances of successor activities scheduled to begin before the activities which precede them (representing 1.8% of all activities in the schedule). Without management attention, this obviously impossible situation has the potential to cause serious project delays. To improve the integrity and robustness of the schedule, we recommend correcting these errors.

Analysis Warning: To maximize the effectiveness of the HCP analysis, we recommend that these instances be reviewed and corrected, if necessary, before resubmitting the schedule for a full HCP analysis.

Note: Each pair of activities is listed with the predecessor first, followed by its successor.

# Activity ID WBS % Completed Start Date End Date
11842019_R.8.15.70.0%04/29/2010 04:12pm 05/13/2010 04:12pm
Install New T&L Coat Track System #9 & #10 at the location shown on the drawing
1822019_R.8.15.50.0%12/16/2009 04:12pm 12/21/2009 04:12pm
Dock Date for pumps
21922019_S.40.0%10/22/2009 08:00am 10/22/2009 05:00pm
Eng Qual
1912019_S.10.0%10/15/2009 08:00am 10/21/2009 05:00pm
Order YNH
31962019_V0.0%12/28/2009 08:00am 01/15/2010 05:00pm
Convert NGR Channel to Norob Dr. in Diffusion (optional)
1952019_U0.0%12/07/2009 08:00am 12/25/2009 05:00pm
Convert Channel B - 2 from WM Nit to LT Ox in Diffusion

 


2.5. Activities with Calendar Inconsistencies

We found that the specified durations of all activities are consistent with their defined start date, end date and the schedule's calendar. This is a good indicator of high schedule integrity.

 


2.6. Overdue Activities

We identified the following 3 overdue activities (representing 1.8% of all activities in the schedule), which should have already been started as of the effective date of this analysis (September 12, 2009).

# Activity ID WBS Start Date End Date
1192019_E.209/10/2009 08:00am 09/10/2009 05:00pm
Relocate the LXK Ultra #3 with its adjacent table to an empty location in the 7in Photo area
2202019_E.309/11/2009 08:00am 09/11/2009 08:00am
LXK Ultra #3 RTP
31812019_R.8.15.409/10/2009 08:00am 09/10/2009 08:00am
Dock date for Nowpak

 


3. HCP Critical Path Analysis Report

3.1. HCP Critical Path Analysis Overview

Key Schedule and Analysis Dates

Earliest start date in schedule: August 18, 2009
Scheduled project end date: May 25, 2010
Date range analyzed: August 18, 2009 – May 25, 2010
Effective date of analysis: September 12, 2009

Note: For the purposes of reporting on progress-related issues, the effective date of analysis applied was September 12, 2009 and not today's date.

Activity and Link Counts

Number of activities in schedule: 166
Number of links in schedule: 188

Critical and Near-critical HCP Paths Found in the Schedule

Total HCP paths identified: 174
Redundant paths ignored: 111
Unique paths analyzed: 63

 

Critical and Near-critical HCP Paths Histogram


Number of Paths

4
3
2
1
0.020.340.551.3

Path Duration Float (Days)

 


3.2. Activities in the HCP Critical Paths

The 2 paths found in the schedule with the longest duration (180.1 days), referred to herein as the "HCP critical paths," are not both identical to the conventional (CPM) critical path(s). This means that there are 2 paths in the schedule (consisting of a total of 52 activities) requiring urgent management attention. Without this attention, the on-schedule completion of the project is in jeopardy.

# Activity ID WBS % Completed HCP Path # CPM Critical
1142019_D.1100.0%1Yes
PO Submitted
2152019_D.2100.0%1Yes
Relocate the LXK Ultra #1 with its adjacent table to an empty location in the 7in Photo area
3162019_D.3100.0%1Yes
LXK Ultra #1 RTP
4192019_E.2 0.0%1No
Relocate the LXK Ultra #3 with its adjacent table to an empty location in the 7in Photo area
5212019_E.4100.0%1Yes
Relocate LXK Ultra WIP Rack to an area designated on the drawing next to LXK Ultra #3
6372019_H.5.2 0.0%1No
WS #8 reverse direction
7382019_H.5.3 0.0%2No
Remove WS # 7 to 9in Implant Grey Area to be used in 7in Photo Area after 7in Etch/Strip extension is Built Out
8392019_H.5.4 0.0%1No
Relocate WS #12 to WS#7 location
9402019_H.5.5 0.0%1No
Remove WS # 11 to 9in Implant Grey Area to be used in 7in Photo Area at the Tegal 903E2 after 7in Etch/Strip extension i
10412019_H.5.6 0.0%1No
Relocate 36x18 inch WIP Rack to the North Clean Room Air Return Wall by Column C2 in the 7in Photo
11422019_H.5.7 0.0%1No
Relocate 48x18 inch WIP Rack to temporary location at the North Clean Room Wall next to the 36x18 WIP Rack then will be
12432019_H.5.8 0.0%1No
Relocate Engineering WIP Rack to a Temporary Location on the North Clean Room Wall next to the 48x18 WIP Rack until 7in
13442019_H.5.9 0.0%1No
Remove House Vacuum Cabinet to 7in Photo Area between column line B1 and A1 on the West Outside Wall
14452019_H.5.10 0.0%1No
Stainless Steel Exhaust Order for Storage Cabinets
15462019_H.5.11 0.0%1No
Dock Date
16472019_H.5.12 0.0%1No
Disconnect and Temporally remove Acid Storage Cabinets from 7in Etch/Strip area, these Cabinets will be relocated in the
17482019_H.5.13 0.0%1No
Relocate Waste and Flammable Containers to a location next to Spec Book Table in 7in Etch/Strip
18492019_H.5.14 0.0%1No
Relocate Supplies Containers and CorrLXKve Container by the entrance door to a location next to the Waste and Flammable
19712019_I25.0%1Yes
construction of 7in ETCH/Strip Extension (w/ ramp #4)
20762019_K.3 0.0%1Yes
Tool hookup in 7" Photo
21772019_K.4 0.0%1Yes
Equipment/Process Qual
22782019_K.5 0.0%1Yes
RTP
231252019_R.1.1.1 0.0%1Yes
Shutdown Nitro 1,2,3,4 and decon, remove and dispose
241262019_R.1.2 0.0%1Yes
Remove WS #18 Computer and Table to 9in Implant Grey Area temporarily to make room for wall construction in the 9in Phot
251272019_R.1.3 0.0%1Yes
Move Nano with work table WS #21 and table and WIP Rack off the 9in Clean Room Wall
261282019_R.1.4 0.0%1Yes
Relocate WIP Rack next to WS #22 Table and Work Table
271292019_R.2 0.0%1Yes
Plastic the 7in Etch/Strip area
281302019_R.3 0.0%1Yes
Demo of the 7in Etch/ Strip area
291322019_R.5 0.0%1Yes
Asbestos Abatement
301332019_R.6 0.0%1Yes
Construction of the 9in Photo Extension.
311342019_R.7 0.0%1Yes
9" Photo Room Qual
321362019_R.8.1 0.0%1Yes
Install New Stainless Steel Shower
331372019_R.8.2 0.0%1Yes
Relocate Nano Inspection Machine and Table next to the shower in 9in Photo
341382019_R.8.3 0.0%1Yes
Relocate WS #21 Computer and Table Next to Nano
351402019_R.8.5 0.0%1Yes
Install New TMC Isolation Table at West End of 9in Photo next to Optistation Inspection #3 for inspection station 1
361432019_R.8.6.2 0.0%1Yes
Remove Optistation Inspection #1 and relocate to the new Isolation Platform just installed next to Optistation Inspectio
371472019_R.8.7 0.0%1Yes
Remove Optistation Inspection #1 TMC Isolation Table and Install it next to the new location of Optistation Inspection #
381532019_R.8.8.5 0.0%1Yes
Install New Optistation V Inspection Station #4 onto the TMC Isolation Table relocated
391542019_R.8.8.6 0.0%1Yes
Eng Qual Opti V #4
401582019_R.8.9.2 0.0%1Yes
Install New TMC Isolation Table for Ultratech Stepper in the location where Optistation Inspection #1 was removed
411602019_R.8.9.4 0.0%1Yes
Install Ultratech Stepper #5 on the Isolation Platform installed next to Ultratech Stepper #7 at the designated location
421612019_R.8.9.5 0.0%1Yes
Eng Qual Ultratech #5
431622019_R.8.9.6 0.0%1Yes
RTP
441642019_R.8.10 0.0%1Yes
Remove Shower Assembly that is located across from column A4 in the 9in Photo Area and install it in the 9in Etch/Strip
451662019_R.8.12 0.0%1Yes
Remove Clean Room Wall that was next to the Shower in the 9in Photo Area and repair any imperfections to the Wall and Ce
461692019_R.8.13.2 0.0%1Yes
Remove Yellow M Oven and Slide it to the Right along with the WS #24 Computer and Table and the Work Table and reconnect
471742019_R.8.14.2 0.0%1Yes
Remove Batch Develop #1 & #2, SRD's, services and associated equipment, Slide it to the Right along with WS #25 Comput
481842019_R.8.15.7 0.0%1Yes
Install New T&L Coat Track System #9 & #10 at the location shown on the drawing
491852019_R.8.15.8 0.0%1Yes
Eng Qual T&L Coat Track
501862019_R.8.15.9 0.0%1Yes
RTP
511942019_T 0.0%1Yes
Remove Shower Assembly located in the 9in Etch/Strip and install the shower from 9" Photo
521972019_W 0.0%1Yes
Finish MS

 


3.3. Opportunities for Bringing Forward the Schedule's End Date

Our HCP critical path analysis revealed lags and/or constraints in the HCP critical paths which may provide opportunities for bringing forward the project's end date.

The following four types of opportunities may appear below:

Type of Opportunity Description & Recommendation
Link There is a gap of time between the end of this activity and the start of its successor. Recommendation: Look for opportunities to eliminate the lag between these activities and/or to eliminate the constraint on the successor's start date.
End There is a gap of time between the end of this activity, which is the last activity in the longest HCP path, and the end of the project schedule. Recommendation: Look for opportunities to eliminate constraints on the CPM critical path and thus bring forward the schedule's end date.
Start There is a gap of time between the start of the schedule and the start of this activity, which is the first activity in the longest HCP path. Recommendation: Look for opportunities to eliminate the constraint on starting this activity.
Today There is a gap of time between today (or August 18, 2009, the earliest date in the range of this analysis) and the start of this activity, which is the first activity in the longest HCP path. Recommendation: Look for opportunities to eliminate the constraint on starting this activity.

 

The schedule's end date could possibly be brought forward by up to 20.8 days, by addressing lags and/or constraints related to the following activities which are within the HCP critical path:

# Type Activity ID WBS % Completed Start Date End Date Differential HCP Path #
1Link212019_E.4100.0% 09/11/2009 09:36am 5.81
Relocate LXK Ultra WIP Rack to an area designated on the drawing next to LXK Ultra #3
372019_H.5.2 0.0%09/21/2009 08:00am  
WS #8 reverse direction

The following schedule shortening opportunities are no longer relevant as they are prior to the effective date of analysis (September 12, 2009):

# Type Activity ID WBS % Completed Start Date End Date Differential HCP Path #
1Start    08/18/2009 08:00am 12.01
Start of Schedule
142019_D.1100.009/03/2009 08:00am  
PO Submitted
2Link142019_D.1100.0% 09/03/2009 08:00am 3.01
PO Submitted
152019_D.2100.0%09/08/2009 08:00am  
Relocate the LXK Ultra #1 with its adjacent table to an empty location in the 7in Photo area

 


3.4. Overlapping Activities in the HCP Critical Paths

We found no instances of parallel activities in the HCP critical paths. This indicates a plan with relatively low risk of falling behind schedule at any particular point in the project. However, we recommend seeking out opportunities where activities found in the HCP critical paths may be performed in parallel. While doing so will add a degree of risk at these particular points in time, it will add a buffer at the end of the project, thus increasing the probability of completing the entire project on schedule.

 


3.5. Activities in the HCP Near-critical Paths

Of the schedule's 166 activities, we identified 52 activities which are within the 2 HCP critical paths (detailed above in section 3.2) and another 20 activities within 61 "HCP near-critical paths" (detailed in this section). This indicates a risky project, and these activities require urgent management attention.

The activities in the following table are listed in decreasing order of importance, i.e., those listed first in the table require the most management attention in order to ensure successful project completion. This order is determined by the "HCP duration float" of the HCP path in which the activity appears. The HCP duration float is the difference in duration between the longest HCP path (i.e., the HCP critical path) and the particular HCP near-critical path in which the activity appears. In other words, the most critical activities to manage are those which appear within the HCP near-critical paths with the smallest duration float.

We strongly recommend that the "hidden critical activities" listed in the following table (and those listed in section 3.2, above) be used as the basis for focusing management attention in the following ways:

# Activity ID WBS % Completed HCP Path # HCP Path Duration Float
1182019_E.1100.0%3 2.00
PO Submitted
282019_C.1100.0%5 3.20
PO Submitted
3612019_H.9.4 0.0%7 5.30
Exhaust purchase and delivery
4622019_H.9.5 0.0%7 5.30
Relocate and Install (slide left) 944 Strip Station to the left Aprox. 9.0 Ft next to the Technician WS Computer Table
5632019_H.9.6 0.0%7 5.30
Install (1) SRD's (Spin Rinser Dryer) at the 944 Strip Station location as shown on the drawing
6642019_H.9.7 0.0%7 5.30
Temporarily relocate the WIP Rack next to the 944 Strip Station (to be determined by area supervisor) and then after the
71822019_R.8.15.5 0.0%815.00
Dock Date for pumps
8582019_H.9.1 0.0%1015.30
PO Submitted
9592019_H.9.2 0.0%1015.30
Waste Collection Drain Replacement
10602019_H.9.3100.0%1116.30
PO Submitted for tool
111752019_R.8.14.3 0.0%1217.00
Eng Qual Batch Develop Bench
121762019_R.8.14.4 0.0%1217.00
RTP
13742019_K.1 0.0%2425.50
PO Submitted
14752019_K.2 0.0%2425.50
Run Services to 7" Etch Extension
151702019_R.8.13.3 0.0%2527.50
Eng Qual Yellow M Oven
161712019_R.8.13.4 0.0%2527.50
RTP
171552019_R.8.8.7 0.0%3943.00
RTP
181442019_R.8.6.3 0.0%4446.00
Eng Qual Opti V #1
191452019_R.8.6.4 0.0%4446.00
RTP
201312019_R.4 0.0%6177.40
PO For Asbestos Submitted

 


3.6. Difficult-to-Track Activities

We identified 19 activities as "difficult-to-track." These are activities which have a duration longer than 8.6 days (we determined this threshold based on our overall analysis of this schedule). We recommend subdividing these activities into a number of activities of shorter duration in order to improve management monitoring and control of these activities.

# Activity ID WBS Calendar Activity Duration (Days) % Completed
1222019_F 45.050.0%
9" Photo Engineering Design (QAC)
21332019_R.6 40.0 0.0%
Construction of the 9in Photo Extension.
3712019_I 30.025.0%
construction of 7in ETCH/Strip Extension (w/ ramp #4)
4752019_K.2 15.0 0.0%
Run Services to 7" Etch Extension
5772019_K.4 15.0 0.0%
Equipment/Process Qual
61952019_U 15.0 0.0%
Convert Channel B - 2 from WM Nit to LT Ox in Diffusion
71962019_V 15.0 0.0%
Convert NGR Channel to Norob Dr. in Diffusion (optional)
8612019_H.9.4 11.0 0.0%
Exhaust purchase and delivery
9812019_L.2 10.0 0.0%
Run Services to the 7" Etch Extension
101112019_P.4 10.0 0.0%
Install the new Sol. Fusion Cook Tool in the 9in Implant Area
111172019_Q.3 10.0 0.0%
Inst. #9 pre-IQ
121192019_Q.5 10.0 0.0%
Install Inst. Strip #9, 7" photo to location next to WS #14
131302019_R.3 10.0 0.0%
Demo of the 7in Etch/ Strip area
141322019_R.5 10.0 0.0%
Asbestos Abatement
151742019_R.8.14.2 10.0 0.0%
Remove Batch Develop #1 & #2, SRD's, services and associated equipment, Slide it to the Right along with WS #25 Comput
161842019_R.8.15.7 10.0 0.0%
Install New T&L Coat Track System #9 & #10 at the location shown on the drawing
17702019_H.10.3 9.978.0%
Plastic 7" photo all Walls Pre CM
18932019_M.7 9.0 0.0%
Matrix tool pre-install
19552019_H.7 8.8 0.0%
The Technician WS Table will be swapped with WS #19 Table and slide left Aprox. 65in. to allow the 944 Strip Station to

 


3.7. Unstarted (Overdue) Paths

We identified 9 unstarted (overdue) paths in the schedule. This could indicate a number of different potential problems which might require urgent management attention.

# HCP Path # Included Activities Path Duration
Float (Days)
12474, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 19725.50
23674, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 18240.50
33774, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 19742.50
45474, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 19753.00
55974, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 155, 19768.50
66074, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 144, 145, 19771.50
761131, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 19777.40
862131, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 18292.40
963131, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 19794.40

 


3.8. Identified HCP Paths

The following table lists the unique HCP paths identified in our analysis, and the activities included within each one.

Notes:

HCP Path # Included Activities Path Duration
(Days)
Path Duration
Float (Days)
1 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197180.10 0.00
2 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197180.10 0.00
3 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197178.10 2.00
4 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197178.10 2.00
5 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197176.90 3.20
6 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197176.90 3.20
7 61, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197174.80 5.30
8 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182165.1015.00
9 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182165.1015.00
10 58, 59|| 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197164.8015.30
11 60, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197163.8016.30
12 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197163.1017.00
13 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197163.1017.00
14 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182163.1017.00
15 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182163.1017.00
16 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182161.9018.20
17 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182161.9018.20
18 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197161.1019.00
19 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197161.1019.00
20 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197159.9020.20
21 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197159.9020.20
22 61, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182159.8020.30
23 61, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197157.8022.30
24 74, 75, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197154.6025.50
25 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 197152.6027.50
26 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 197152.6027.50
27 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 197150.6029.50
28 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 197150.6029.50
29 58, 59|| 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182149.8030.30
30 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 170, 171, 197149.4030.70

Note: This table contains only the first 30 identified HCP paths. The complete list of all 63 HCP paths is available upon request as an appendix to this report at no charge.

 


3.9. Redundant HCP Paths

We identified 111 redundant HCP paths in this schedule.

A redundant HCP path is a path (e.g., Path X) whose entire set of included activities appears within a different path containing a greater number of activities (e.g., Path Y), as in the following example:



Path X: A → B → E → F
Path Y: A → B → C → D → E → F
Path X is redundant.

The following table lists the redundant HCP paths identified in our analysis, and the activities included within them.

Notes:

HCP Path # Included Activities Path Duration
(Days)
Path Duration
Float (Days)
1 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197179.90 0.20
2 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197179.90 0.20
3 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197177.90 2.20
4 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197177.90 2.20
5 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197176.70 3.40
6 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197176.70 3.40
7 61, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197174.60 5.50
8 8, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197173.90 6.20
9 8, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197173.70 6.40
10 8, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197172.90 7.20
11 8, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197172.70 7.40
12 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182164.9015.20
13 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182164.9015.20
14 58, 59|| 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197164.6015.50
15 60, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 185, 186, 194, 197163.6016.50
16 14, 15, 16, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197162.9017.20
17 14, 15, 16, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197162.9017.20
18 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182162.9017.20
19 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182162.9017.20
20 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182161.7018.40
21 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182161.7018.40
22 18, 19, 21, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197160.9019.20
23 18, 19, 21, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197160.9019.20
24 8, 37, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197159.7020.40
25 8, 37, 38, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 175, 176, 197159.7020.40
26 61, 62|| 63|| 64, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182159.6020.50
27 8, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182158.9021.20
28 8, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182158.7021.40
29 8, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 138, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182157.9022.20
30 8, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 71, 76, 77, 78, 125, 126, 127, 128, 129, 130, 132, 133, 134, 136, 137, 140, 143, 147, 153, 154, 158, 160, 161, 162, 164, 166, 169, 174, 184, 182157.7022.40

Note: This table contains only the first 30 redundant HCP paths. The complete list of all 111 redundant HCP paths is available upon request as an appendix to this report at no charge.

 


3.10. Enhanced Schedule File

Accompanying this report, please find a modified Primavera schedule file, containing the original schedule modified with the following additions:

 


Disclaimer

Neither HCP Project Management Consulting (HCP) nor its employees shall be liable for any damages or costs of any type arising out of, or in any way connected with, your use of any analysis report prepared by HCP.

The information and recommendations within the reports are provided for informational purposes only. All responsibility as to their use, or any repercussions resulting from their use, is borne by you alone.

Please note that the entire analysis is based solely on information contained within the project schedule file received from you. There may be numerous other factors and considerations beyond this data which may influence the project, its progress, its management and its success.

All intellectual property contained within, or delivered alongside, our reports is licensed to you and not sold to you. You are hereby granted a non-exclusive, non-sub-licensable, non-transferable, revocable, limited license to use the intellectual property in the reports subject to this disclaimer. HCP reserves all rights not expressly granted to you herein.

The specifications of the analysis reports will be considered the Confidential Information of HCP. You agree to: (i) hold and maintain in strict confidence all this Confidential Information; and (ii) not use any of this Confidential Information in any manner except for internal company use.

You agree that you will not modify any reports received from HCP, create derivatives of the reports, adapt the reports, re-arrange, reverse engineer or otherwise alter the reports; nor shall the user sell, assign, rent, lend, sublicense, copy or otherwise transfer the reports or any part thereof or use it in any other manner.


HCP Project Management Consulting

Tel. 1-888-HCP-2080
Email: info@hcp-consulting.com
Web: www.hcp-consulting.com